Caveman Planning Good! Made in Jozefoslaw with Tokens, Coffee and OpenMercato Skills during AITechLeaders training.

CPG
  • Help
  • Sign in
All help topics

The Test dataset's planning week

Test's generated datasets, tiny and realistic, plan one plant the way a weekly MRP run would. Customers order every weekday, but production and purchasing are planned once a week, at Thursday's planning run. That choice decides which documents you find open on a given day.

One planning cycle

  1. Thursday, week 1

    Planning run

    Creates week 2's production orders, up to next week's need plus safety stock, and one purchase order per supplier.

  2. Monday, week 2

    Steel arrives

    Steel Service Centre's order is received in full.

  3. Tuesday, week 2

    Supplies arrive

    Industrial Supplies Wholesale's order is received in full.

  4. Monday to Thursday, week 2

    Production

    Intermediates are completed on Monday and Tuesday, after the receipts, and finished products on Wednesday and Thursday.

  5. Every weekday, week 3

    Shipments

    Customer orders ship from the stock week 2 built.

On Thursday of week 2 the next run plans week 3: the cycle repeats every week.

Each Thursday plans the next week, and that week's production stocks the week after it.

What “Today” holds, day by day

A reset writes the history up to yesterday and then, on today, one partial document of each kind, as a user would leave them. A partly received purchase order needs an order created before today and not yet due, so it follows the planning week.

Mon
Tue
Wed
Thu
Fri
Sat
Sun
  • Planning run
  • Purchase order received
  • Partly received purchase order
  • None
Monday to Sunday: Thursday's run, the receipts it plans, and whether a reset on that day leaves a partly received purchase order.
  • MondayPartly received purchase order

    Steel's order from Thursday is due today: its first line is received.

  • TuesdayPartly received purchase order

    The supplies order from Thursday is due today: its first line is received.

  • WednesdayNone

    Both of Thursday's orders were received on Monday and Tuesday.

  • ThursdayNone

    Today's run creates next week's orders, and nothing is received on the day an order is created.

  • FridayPartly received purchase order

    Thursday's orders wait for Monday: the first line of steel's order is received.

  • SaturdayPartly received purchase order

    As on Friday: the first line of steel's order is received.

  • SundayPartly received purchase order

    As on Friday: the first line of steel's order is received.

Whatever the day: the overdue top-up purchase order and the open purchase requisitions are there, and a partly completed production order whenever one is in progress.

Why weekly, at Thursday's run

Weekly planning keeps the documents few enough to read: one production order per made item and one purchase order per supplier each week. Daily production orders would make about three times as many.

The price is the gap on Wednesday and Thursday. Ordering two weeks ahead would keep a partly received purchase order open every day, but it changes the cadence, so the datasets keep the weekly one.

To see a partial receipt, reset Test on a day from Friday to Tuesday: a reset generates the dataset for the day it runs.